South Gippsland Water Baxter Beach Outfall installation

Duties:

  • Survey existing damaged outfall.
  • With consultation with South Gippsland Water develop alternative offshore discharge pipeline taking into account the shallow water and rough sea conditions.
  • Installation of pipe section using flotation devises and hauling offshore.
  • Sinking and joining new pipeline to old pipe work at beach low water point.

Photos:

pic-South Gippsland Water Baxter Beach Outfall installation

Baxter beach outfall installation.

pic-South Gippsland Water Baxter Beach Outfall installation

200mm dia HDPE pipe encased in 230 ID Cast Iron Articulated pipe.

pic-South Gippsland Water Baxter Beach Outfall installation

Diver attaching flotation to pulling head for floating into position through reef.

pic-South Gippsland Water Baxter Beach Outfall installation

50m HDPE pipe in position and diver removing flotation

pic-South Gippsland Water Baxter Beach Outfall installation

Offshore SS discharge point (Duckbill to be installed)

pic-South Gippsland Water Baxter Beach Outfall installation

Articulated covered pipe was easily profiled through rocky reef

pic-South Gippsland Water Baxter Beach Outfall installation

Pipe section quickly self buried through sand with wave action.

pic-South Gippsland Water Baxter Beach Outfall installation

Cast iron pipe SS adaptor to 450 supply flange.