PP1 Australia Guam Cable for Pipe International

Duties:

  • Assist Coe Drilling Australia, drilling operations including survey and seabed profiling.
  • Run proving mandrel and install braided hauling line.
  • Excavate to expose exit point area to receive bellmouth.
  • Install 18mm wire 100m offshore ready for connection to transmission cable.
  • Install completion piece and bellmouth ready for cable installation
  • Tow floating cable from ship ‘Tyco Durable’ 500m offshore to pick up point and connection to hauling wire.
  • Direct hauling operations from offshore and removing cable flotation.
  • Install Stopper at holdback block 400m from bellmouth.
  • Install articulated pipe for 450m offshore.
  • Carry out video survey off completed work.
  • Install steel completion piece and flange to fit cable installation bellmouth.
  • Install 6m x 150mm dia pin pile to support HDPE conduit during cable installation and plough down
  • Install split pipe adaptor and Articulated pipe protection.
  • Carry out seabed survey on cable to 30m of water depth.

»Testimonial on the PP1 Australia Guam Cable for Pipe International project

pic-Australia to Guam Cable

Sizing mandrel on deck of 'MV Avalon'

pic-Australia to Guam Cable

Towing floating transmission cable and connected to 18mm hauling wire 100m from exit point.

pic-Australia to Guam Cable

Recovered 1.5kl of 20mm braided rope line from wire installation.

pic-Australia to Guam Cable

Exit point with bellmouth installed and hauling wire positioned offshore

pic-Australia to Guam Cable

HDD Exit point with split flange adaptor and articulated pipe installed.