DivingCo-Header

Alacatel-Lucent

Cable Landing for Gondwana at North Narrabeen for the Australia New Caledonia cable network.

Conduit proving at Narrabeen of the ocean conduit for Gondwana

Conduit proving at Narrabeen of the ocean conduit for Gondwana.

Diving Duties:

  1. Locate exit point offshore Narrabeen.
  2. Run proving mandrel and change hauling rope.
  3. Install 22mm hauling wire to be 100m offshore and install bellmouth on exit point.
  4. Assist with cable landing operations
  5. Install sealing flange and articulated pipe and video all components.
Conduit proving at Narrabeen of the ocean conduit for Gondwana

Cable vessel Ile De Re passing the bight of the cable overboard after completion of cable laying of the Australia New Caledonia cable.

Exit flange with split sealing flange and articulated pipe installed.

Exit flange with split sealing flange and articulated pipe installed.